Industries/Mining
Open-pit · Underground · Processing — sealed deliverables

Where the tonnage
doesn't tolerate noise.

Mining operations don't run on guesses. A halted shovel costs $80-150 K per shift. A dropped dragline counterweight ends careers, projects, and permit applications. A mill-module install slipping past the planned tie-in window cascades across the entire project schedule. We engineer the lift plans for that exposure — open-pit to shaft, primary crusher to filter press. Standards cited inline, sealed before the crane rolls.

CSA M421

Canadian mining safety reference applied

ISO 17757

Autonomous mining machinery — referenced

24 h

Emergency lift plans — Canadian mine sites

0

Operator briefings without a sealed plan in hand

01 · What's at risk

Six exposures every mine plan must answer.

Mining engineering is risk arithmetic across kilometers of pit and meters of shaft. The exposures below are the line items that show up on every project's risk register — and on every regulator's annual review. Each Maxor deliverable in this vertical addresses them explicitly.

01

Production halt cost

$80-150 K per shift for a major shovel down. $250 K+ per day for a mill stoppage at concentrator scale. The lift plan is rarely the bottleneck — but when it is, it's the most expensive bottleneck in the operation.

02

Worker safety — surface + underground

Struck-by, crushing, fall-from-height, confined-space exposure. Each incident triggers provincial inspector notification (CNESST in Quebec, MOL Ontario, BC OHS), insurance reserve hit, and a project-wide stand-down. The plan exists to make these impossible.

03

Tailings + water — ECCC reportable

Failed mill-component lift over an active TSF, dropped equipment into a polishing pond, hydraulic release on a haul road : MMER reportable events. ECCC monitors closely. The lift plan's contingency matrix is the document that proves you saw it coming.

04

Permit + regulator memory

Provincial ministry, ECCC, MMER inspector, ICMM signatories — every Canadian mining regulator has institutional memory. A poorly-engineered lift becomes the file that follows your next amendment application. Sealed deliverables — every time.

05

Schedule + capex on capital projects

Mine-build capital projects carry $millions per week in carrying cost. A re-spec triggered by a discovered geometry conflict or as-built mismatch is 1-3 weeks. Engineering catches conflicts in CRANEbee 3D before the crane mobilizes — not after.

06

ICMM + ESG audit posture

ICMM Mining Principles + Towards Sustainable Mining (TSM) audits track engineering rigor as one of the substantive ESG signals. The lift plan is part of the assurance file — not just the project file.

02 · Operations served

Six operation archetypes. Standard methodology, every one.

Mining operations cluster into recurring engineering patterns. Each archetype has its own load-case profile, regulatory framing, and deliverable shape. The methodology adapts ; the rigor doesn't.

Open-pit

Shovel + truck + dragline maintenance lifts

Shovel propel-frame, bucket, swing-circle replacements. Haul-truck frame swaps, suspension struts, engine pulls. Dragline assembly + counterweight handling. Mobile-crane access on rough pit roads ; ground-bearing analysis on prepared pads.

Underground

Shaft + headframe equipment

Headframe sheave-wheel installs, skip and cage replacements, hoist-house gear changes, ventilation-shaft equipment. Confined-site lifts in active mine yards. Cold-weather lift envelopes for northern operations.

Processing

Primary crusher + mill module installs

Gyratory and jaw crusher replacements, SAG / ball mill component lifts, motor and trunnion handling. Modular mill builds with prefab SPMT-to-crane handoff. CRANEbee 3D mandatory before mobilization.

Conveyor

Overland conveyor + transfer-tower equipment

Drive-pulley + tail-pulley installs, take-up + tensioner components, transfer-tower steel and chutes. Tandem-crane operations on tight transfer-station footprints.

Tailings + water

Tailings + water-treatment equipment

Thickener mechanisms, filter-press lifts, pump and valve installs at TSF inlets / outlets. Engineered to avoid exposure to active tailings line of fire. Contingency matrix written against MMER reportable thresholds.

Capital + brownfield

Mine-build + expansion + relocations

Equipment delivery to greenfield builds, brownfield-expansion ties to live operations, mine-life-extension equipment relocations. Multi-stakeholder coordination — contractor + operator + regulator + community.

On the ground

Mining in the field

From sector context to the lifts we engineer — a look at where this work happens.

Open-pit mining — heavy haul
Open-pit mining — heavy haul
Underground mine tunnel
Underground mine tunnel
Mining haul truck
Mining haul truck
Ore processing mill
Ore processing mill
Heavy lift — crane hook detail
Heavy lift — crane hook detail
Crawler crane — heavy lift
Crawler crane — heavy lift
03 · Standards we reference

The standards we work to.

Engineering rigor in mining is grounded in a documented standards stack — provincial, federal, and industry-association. Every Maxor deliverable cites the applicable standards inline. These are the ones that govern a mine-site lift.

CSA M421

Use of electricity in mines

Canadian standard for electrical equipment and installations in mines and mineral processing plants. Cited on every lift that interacts with energized equipment underground or in concentrator buildings.

ISO 17757

Earth-moving machinery — autonomous + semi-autonomous

Functional safety standard for autonomous and semi-autonomous earth-moving and mining machinery. Cited when planning lifts adjacent to autonomous haul-truck fleets.

RSST · Reg 854

Provincial mine regulations (Quebec + Ontario)

Quebec RSST (sécurité dans les mines) ; Ontario Regulation 854 (Mines and Mining Plants under OHSA). Both cited on every plan we ship in their respective jurisdictions.

ASME B30.5 / Z150

Mobile crane operation + Quebec lift-plan code

ASME B30.5 — mobile crane safety. Quebec Norme Z150 — provincial lift-plan code. Both cited on every mining lift plan we ship.

MMER

Metal and Diamond Mining Effluent Regulations

Federal Fisheries-Act regulation governing effluent from Canadian metal and diamond mines. We don't author MMER reports — we plan to avoid the events that trigger them.

ICMM + TSM

Mining Principles + Towards Sustainable Mining

ICMM Mining Principles (international) and TSM (Mining Association of Canada). The engineering posture our lift plans embed aligns with both assurance frameworks — referenced in our deliverables for client ESG files.

04 · Capabilities applied

Four capability lines. One mining engagement.

Maxor's four capability lines (lift planning, CRANEbee distribution, Murlink distribution, software) all show up on a typical mining engagement. Here's how each one earns its place on a major program.

01
Lift planning

Sealed plans + emergency response

Single-pick to multi-crane tandem. Same-day emergency tier available across Canadian mine sites when a shovel-down event halts the pit. Z150 / B30.5 cited inline.

02
CRANEbee®

Distribution + training + implementation

Mill-module installs, primary-crusher swings on tight footprints, multi-crane tandem on dragline rebuilds — all modeled in CRANEbee. Drone-photogrammetry site capture where the as-built pit doesn't match the design CAD.

03
Murlink®

Distribution + advisory + training

Dyneema® synthetic chains for quarry-block handling, equipment lifts where steel-chain weight slows the crew on rough terrain, and processing-area lifts where conductivity near energized busbars is a hazard. Authorized Quebec distribution.

04
Software

Deterministic engineering platform

The Maxor software line (Heisen, Maxor Audit, Maxor Ground) provides the audit-grade evidence substrate that ICMM and TSM assurance files consume — sealed audit trails, regulator-readable, sovereign deployment.

05 · Custom solutions

Beyond the four pillars — software built for your operation.

The four service pillars cover the lift. But most mine operators carry a software gap the off-the-shelf vendors never close. We build it — custom applications, integrations, and managed services, same engineering posture, same team from kickoff to go-live, sovereign by default. Engineered in Canada, owned by you.

Heisen — our deterministic intelligence layer — is optional on any build: embed it or not, your call. Either way it plugs into a fresh custom app or your existing third-party software via API.

Discuss a custom build
01

Ore-tracking + grade reconciliation

Tracks material from pit face to mill feed, reconciling grade and tonnage at each transfer — closing the gap between the resource model and what the mill actually receives.

02

Fleet dispatch + haulage optimization

Optimizes shovel-truck assignment and haul-cycle routing in real time — fewer empty runs, shorter crusher queues, more tonnes per shift, all on an auditable decision trail.

03

ESG + tailings-monitoring platform

Consolidates tailings-facility instrumentation, water-quality data, and ICMM / TSM reporting into one assurance dashboard — the evidence file the auditor asks for, generated continuously.

[Engage]

Scope your mining engagement.

Tell us the operation, the equipment, and the schedule. A senior lead responds within one business day with a scoped engagement and a path to first deliverable.